Thursday, 4 August 2016

A LONG OVERDUE UPDATE

Well it's been a super long time since the last update but better late than never, hey? We've come along way since piers and a portaloo but I'll give you an update in chronological order.

11 April
We got plumbing, the beginnings of form work and waffle pods were delivered.


15th April
Formwork continued and waffle pods were laid with the rio.

16th April 
And on a Saturday!!! We got the slab poured!! The slab needed to cure for 7 days.

25th April
External plumbing was completed.

28th April
We got a bright orange termite barrier and windows were delivered.

29th April
We got our beautiful, shiny blue steel frames. 


2nd May

Wall frames went up

3rd May 

Roof frames went up




5th May
Windows and doors went in...lots of action that week!

Our altered stacker doors to outdoors and alfresco....was super happy with these!


Our alfresco dining space starting to take shape

 Stacker doors from the kitchen/living/dining

 Bathtub frames

6th May
Bricks delivered

11th May
Brickwork begins



25th May 
Brickwork finishes

No comments: