11 April
We got plumbing, the beginnings of form work and waffle pods were delivered.
15th April
Formwork continued and waffle pods were laid with the rio.
16th April
And on a Saturday!!! We got the slab poured!! The slab needed to cure for 7 days.
25th April
External plumbing was completed.
28th April
We got a bright orange termite barrier and windows were delivered.
29th April
We got our beautiful, shiny blue steel frames.
2nd May
Wall frames went up
3rd May
Roof frames went up
5th May
Windows and doors went in...lots of action that week!
Our altered stacker doors to outdoors and alfresco....was super happy with these!
Our alfresco dining space starting to take shape
Stacker doors from the kitchen/living/dining
Bathtub frames
6th May
Bricks delivered
11th May
Brickwork begins
25th May
Brickwork finishes